Decatur Utilities to begin 2025 natural gas system leak survey Dec. 15


Beginning December 15th, Decatur Utilities will begin a quality control leak survey of the DU natural gas system to ensure public safety and the proper operation of gas lines and meters. This survey is required by the Federal Department of Transportation-Pipeline and Hazardous Material Safety Administration (PHMSA) and The Alabama Public Service Commission (PSC). The survey will continue until approximately March 2, 2026.



ree

As required annually, the survey will check for leaks in all natural gas mains and business/commercial service lines in Decatur. One-fifth of residential service lines are checked each year.


This year's residential survey #2 area is:

  • SW Decatur:

    • North of Clearview St SW & East of Spring Ave SW Dr SW

    • South of 8th St SW & Danville Rd SW

  • SE Decatur:

    • South of 8th St SE Northside R/W & North of Flint Creek.


ree

This project will involve a slow-moving vehicle (approximately 5 MPH) in streets, alleys and highways throughout Decatur. A portion of the work may be conducted at night when traffic is lighter. Some parts of the gas system are only accessible by foot by a technician using handheld gas detection instruments.


The survey work will be conducted by Heath Consultants Inc. of Houston, Texas, a specialist in gas leak detection. Vehicles operated by Heath Consultants Inc. will have signs on the vehicle identifying the company and identifying them as an “Authorized Decatur Utilities Contractor.” In order to check for service line leaks, the Heath Consultants employee will require access to customer property and the gas meter. Heath Consultants employees will have identification and will explain their purpose for being on private property.


During this survey, gas leaks found on Decatur Utilities equipment will be repaired and gas service restored. If gas leaks found are not on Decatur Utilities equipment, the homeowner or business will be notified and gas service will be disconnected until repairs are completed by the homeowner or business.


It is anticipated this work will be completed by March 2, 2026.

 
 
 